Road work, details of which you will find below, are deployed in Town of Brome Lake in Summer and Fall. We ask you to please slow down and respect the signage around the construction sites.
SECTION: near Durkee Street
INVESTMENT:
$50,000
TYPE OF WORK:
WORK DURATION:
2 weeks, in the fall of 2026
OBSTACLES:
SECTION: Various streets
SECTION LENGTH: Variable
INVESTMENT:
$700,000
WORK DURATION:
OBSTACLE:
LIST OF STREETS:
| List of Streets Affected by Roadworks | |
|---|---|
Acadmy | Hastings |
Basin | Hemlock |
Ellson | Kennedy |
Fleury | Luno |
Foster | Stagecoach |
| Gaudord | Tuxen |
Haman | Vallée bleue |
It should be noted that this resurfacing work covers a total of 3.1 kilometers and does not affect the entire street, but rather sections of several dozen meters, depending on the site.
In addition, as part of the annual manual patching contract, minor repairs will be carried out during the summer season. The team will inspect all paved streets to repair potholes and other defects.
ROAD: Chapman, from Iron Hill Road to Center Street
DURATION OF WORK:
The work is scheduled for September and will continue for approximately three weeks.
OBSTACLES:
SECTION: From Boulevard de l’Horizon to Route 243 (Foster Road)
NATURE OF WORK:
DURATION OF WORK:
May 2026
IMPACTS:
For more information:
Project Info Line: 1-866-388-1978
affairesregionales@hydroquebec.com
SECTION: from Route 215 to Brome Road
SECTION LENGTH:
7,5 km
INVESTMENT:
$7.9 million
TYPE OF WORK:
WORK DURATION:
OBSTACLES: